Which beach end will you use this month? On most of Naples Beach the answer stays the same through the holidays. Between 12th and 21st Avenue South, though, the street ends frame this season's public works. 12th Avenue South is fenced for the pier, 17th Avenue South is a construction entrance for the largest sand project the city beach has had in years, and 21st Avenue South, still open, marks roughly where that project stops.
Collier County's Naples Beach Renourishment will spread more than 208,000 tons of sand along 3.5 miles of shoreline, from Doctors Pass south to a point just past 21st Avenue South. The county's own bid documents show that much of the work starts or ends in the Aqualane Shores stretch.
Two Entrances, and Only One Open at a Time
The county advertised the job in August as Bid No. 26-8701. Its project overview asked contractors to build it "using the construction accesses at the 3rd Avenue North and 17th Avenue South public beach accesses in the City of Naples." Those are the only two points where loaded trucks reach the sand. One is north of the Naples Pier, near the center of town. The other is the 17th Avenue South beach end in Aqualane Shores.
A prospective bidder asked during the procurement whether crews could use both entrances at once and work toward each other to speed things up. The county's answer on August 27 was short:
Only one designated beach access point will be allowed at one time during construction.
So the whole 3.5-mile job runs through one street end at a time. While the north entrance is in use, the trucks entering at 3rd Avenue North are a mile and more away. When the work switches to 17th Avenue South, the trucks pass right through the neighborhood's beach end.
On October 13 the Board of County Commissioners awarded the contract to Earth Tech Enterprises Inc. of Fort Myers. It was the lowest responsive bidder of five, and it has done earlier Collier County renourishments. The sand comes by truck from Stewart Mining in Immokalee. The county buys it directly, and the contractor hauls, places, grades and tills it.
The Beach Ends, North to South, This Season
The City of Naples keeps a beach access status table for every street end. The city's current listing for the Aqualane Shores and south Olde Naples stretch, combined with the renourishment plan, looks like this:
- Broad Avenue South. Open, with restrooms. Construction complete.
- 12th Avenue South. Closed for the Naples Pier rebuild.
- 13th Avenue South. Open, with restrooms. Construction complete.
- 14th, 15th and 16th Avenue South. Open. Construction complete.
- 17th Avenue South. Open on the city's list, and designated as the southern construction entrance for the renourishment.
- 18th Avenue South. Open. Construction complete.
- 21st Avenue South. Open, flagged for future reconstruction, and the approximate southern limit of the sand placement.
The restroom ends are 13th Avenue South and Broad Avenue South, on either side of the closed pier access. A walk from 18th Avenue South north to Broad passes the truck entrance, the fenced pier site and the only restrooms nearby, all within about six blocks.
The county says the beach stays open and usable during renourishment, with small areas fenced off where sand is being placed. Spotters will watch the trucks as they move along the beach to each work zone. The fenced areas move with the work, so the closed section on Tuesday may be open again by Friday.
A Project That Waited a Year for the City
This work was meant to happen a year ago. A September 10, 2026 Coastal Advisory Committee agenda says hauling and placement had been planned for early November 2025. The county put off the 2025 Naples Beach Renourishment for one year "due to sequencing of projects with the City of Naples," and moved placement to November 2026.
The city's own projects are easy to spot on the beach. The access table above lists finished reconstruction at most street ends, and north of Central Avenue a stormwater outfall project still has several ends closed. Waiting a year means trucks and graders arrive after much of that street-end work is done, so they don't cross a beach end that is about to be rebuilt.
Florida's Department of Environmental Protection, in its 2023 statewide beach management plan, records the last full nourishment of the Naples segment in January 2022. That project placed 57,330 cubic yards across 2.3 miles. This year's work covers 3.5 miles and reaches farther south, to the 21st Avenue South end.
Hurricanes Helene and Milton also passed through between those two projects. When the county announced the contract, Gulf Coast News reported that both storms brought strong winds and surge that eroded the beach. Resident Bobby Anton told the station that the beach's narrow, sloping profile lets water run onto Gulf Shore Boulevard and adds to flooding there. The county says part of the project cost may be covered as Hurricane Milton and Hurricane Helene work, and it will ask FEMA to reimburse the hurricane-related costs.
What the $8 Million Covers
The county puts the total at about $8 million and has broken it down:
- About $5 million for the Earth Tech hauling and placement contract.
- $2.4 million for sand from Stewart Materials in Immokalee.
- The remainder for engineering design, permitting, inspections and shorebird monitoring.
The money comes from Tourist Development taxes, the bed tax paid by visitors who stay in Collier County lodging. The county may also ask the state DEP to share costs later. The planning documents set aside $17,500 for shorebird monitoring and estimated a construction start of November 1, 2026.
The Calendar Through December
The county's published schedule gives a clear weekly pattern:
| Window | What the county has scheduled |
|---|---|
| Late October | Equipment mobilization and staging setup |
| After mobilization | Sand placement begins |
| Monday to Saturday, 7 a.m. to 7 p.m. | Working hours |
| Sundays | Outside the published working hours |
| November 26 to 29 | Thanksgiving break, no operations |
| Before the end of 2026 | Expected completion |
A 7 a.m. start means crews are already at work during the early beach walk, six days a week. The 7 p.m. finish runs past sunset for all of November and December. Sundays and the four days of Thanksgiving weekend are the only stretches with no crews on the sand before the new year.
The project is due to finish before the end of 2026, while the pier still has months of work ahead. The City's pier rebuild page reports that crews drove the last of 193 reinforced-concrete pilings on October 7, with more than half the concrete poured. Structural work is expected to finish in early 2027, followed by decking, and the city says reopening is on schedule for July 2027. The early stages of that rebuild were covered in our June update from the beach walk. If both schedules hold, the Aqualane Shores stretch will have its new sand by New Year's Day, and the 12th Avenue South end will stay fenced for about six months after that.
Two Blocks Inland
Walking back from the 13th Avenue South end, two familiar restaurants have just reopened after summer work. Naples Daily News reported on October 27 that Sea Salt has reopened at 1186 Third St. S. after an interior refresh, with a new menu from executive chef Josh Zeman. Pazzo! Cucina Italiana reopened at 853 Fifth Ave. S. on October 27 after roof and kitchen renovations, and the restaurant says lunch service will start in December. Pazzo's December lunch start lines up with the last weeks of the sand work.
For questions about the work on a particular stretch of beach, Collier County's Coastal Zone Management section takes calls at (239) 252-2922 and email at [email protected].
If you own a Gulf-front or near-beach home in Aqualane Shores and want to talk about how this season's renourishment and the pier timeline bear on your property, Bates | Ives is glad to share what we are seeing along the 17th Avenue South stretch. Request a private consultation.